Biorefinery
Arbaflame
Scopo: Feasibility study
Capacità: 8 ton/h
Paese: Canada
Anno: 2016
Ruolo: Process Engineer
Arbaframe
Scopo: Feasibility study
Capacity: 65 ton/h
Paese: Kentucky, US
Anno: 2016-2017
Ruolo: Process Engieer
Arbaframe
Scopo: Feasibility study
Capacity: 33 ton/h
Paese: Australia
Anno: 2017
Ruolo: Process Engineer
Consortium
Scopo: Feasibility study
Capacity: 3,5 ton/h
Paese: Netherland
Anno: 2018-2022
Ruolo: Process Engineer
Arbaflame
Scopo: Feedstock preparation feeding/reactors, etc
Capacity: 10 ton/h
Paese: Norway
Anno: 2019-2021
Ruolo: Process engineer and Site manager
Arbaflame
Scopo: FEED (Front End Engineering and Desing)
Capacity: 15 ton/h
Paese: Sweden
Anno: 2021-2022
Ruolo: Project manager
Biorefinery
Cliente
Arbaflame
Arbaflame
Arbaflame
Consortium
Arbaflame
Arbaflame
Scopo
Feasibility study
Feasibility study
Feasibility study
Feasibility study
Feedstock preparation Feeding, reactors, etc.
FEED (Front End Engineering and Design)
Capacità
8 ton/h
65 ton/h
33 ton/h
3,5 ton/h
10 ton/h
15 ton/h
Paese
Canada
Kentucky, US
Australia
Olanda
Norvegia
Svezia
Anno
2016
2016 – 2017
2017
2018 – 2022
2019 – 2021
2021 – 2022
Ruolo
Process Engineer
Process Engineer
Process Engineer
Process Engineer
Process Engineer and site manager
Project manager